Permanent 3D volumetric construction is worth evaluating for an apartment development in France when dwelling layouts can be organised into repeatable module configurations, the design is sufficiently coordinated for manufacturing, and the site can accommodate transport and installation.

The deciding question is not simply whether the apartments can be manufactured as modules. It is whether a full-volumetric approach offers a credible project-wide advantage over comparable hybrid or conventional construction, while meeting French building requirements and the developer’s commercial objectives.

This article focuses on purpose-designed, permanent building modules for apartment developments, rather than temporary site accommodation or converted shipping containers. Volumetric construction should not be assumed to be faster, cheaper or lower-carbon simply because more work takes place in a factory.

French project teams may use terms such as construction hors-site and construction modulaire 3D. These describe approaches within the wider off-site construction sector, not a single structural system or approval route. Article L.111-1(15) of the French Construction and Housing Code defines préfabrication, but that definition alone does not establish the suitability or regulatory acceptance of a particular heavy-steel volumetric system.

Does the Apartment Development Have the Right Conditions for Volumetric Construction?

Repeated Dwelling Types and Building Organisation

Apartment developments with repeated dwelling layouts, service arrangements and structural bays are often reasonable candidates for volumetric assessment.

However, repeated apartments do not automatically translate into repeated modules. The opportunity depends on whether a substantial part of the building can be organised around a manageable family of module configurations, with consistent structural, façade and service interfaces.

Building height is another consideration, but not a standalone decision rule. Low- and mid-rise buildings may offer relatively straightforward arrangements, while taller schemes can introduce greater structural, fire-safety and installation complexity. A high-rise development should not be ruled out solely because of its height, nor should a low-rise project be assumed suitable when its geometry and layouts are highly irregular.

For an initial assessment, the most useful question is whether the building can maintain meaningful module repetition without compromising its architectural, functional or regulatory requirements.

Site Access, Design Stability and Delivery Constraints

The site must support a workable delivery and lifting strategy. Access roads, turning space, crane positions, neighbouring structures and delivery restrictions can influence module dimensions and the installation sequence.

Restricted access does not always rule out volumetric construction. Sequenced deliveries or alternative lifting arrangements may resolve some constraints. Others may prove impractical once transport, structure and site conditions are assessed together.

Design stability matters just as much. The module scope must be sufficiently coordinated and approved for manufacturing before factory release. Late changes to apartment layouts, service positions or façade interfaces can result in redesign, additional module variants and site rework.

A project should therefore be screened across several technical and commercial conditions. Some constraints can be resolved through design adjustments; others may rule out full-volumetric construction if no compliant and feasible solution can be established.

How Does the Dwelling Mix Translate into Module Configurations?

Diagram distinguishing French apartment dwelling types from volumetric modules and reusable module families

Dwelling types do not determine a fixed module count. Module configurations depend on the project design.

French Dwelling Types Are Not the Same as Module Types

French apartment schedules commonly classify dwellings as T1, T2, T3 and so on, based on the number of principal rooms. A T2 typically contains a living room and one bedroom, while a T3 generally contains two bedrooms.

These classifications describe the dwelling, not its manufacturing configuration.

A single apartment may require several volumetric modules. Conversely, apartments with different layouts may share certain standard module configurations. Developers therefore need to distinguish between three quantities:

  • The number and types of dwellings.
  • The number of physical modules required.
  • The number of distinct module configurations that must be designed and manufactured.

The third quantity is particularly important for assessing manufacturing repetition.

A larger apartment does not necessarily translate into a proportionally larger module. Its final configuration will depend on structural spans, internal layout, transport dimensions, service distribution and connections between modules.

A French Example: Résidence Madeleine Didier, Arras

The Résidence Madeleine Didier in Arras provides a useful example of permanent 3D modular housing in France.

The development comprises 42 social housing units across five buildings, assembled using 65 timber-framed 3D modules. According to Pas-de-Calais Habitat, the dwelling mix includes 20 T2 apartments, 20 T4 apartments, one T5 and one T6.

The project was commissioned by Pas-de-Calais Habitat, a French social housing provider (bailleur social), and delivered by Bouygues Bâtiment Nord-Est, with Moon Architecture as architect and TH as module manufacturer. The first module was installed in June 2025, with the complete development delivered in January 2026.

The important lesson is not the numerical ratio of 65 modules to 42 dwellings. It is that a housing schedule must be translated into a buildable module arrangement before developers can assess manufacturing repetition, transport requirements or site assembly.

This completed French project demonstrates a timber-volumetric approach. Its module configurations, structural performance, environmental results and delivery economics should not be transferred directly to a heavy-steel volumetric system without separate evidence.

Where Do Module Variants Come From?

Even when apartment plans appear repetitive, module requirements may vary.

Corner apartments, changes in façade geometry, structural load paths, service-riser locations and accessibility requirements can all affect the module arrangement.

Two apartments with similar internal layouts may therefore need different structural reinforcement, MEP routing or connection details.

For developers, the aim is not to eliminate every variation. It is to identify which variations are necessary, which can be standardised and which materially affect manufacturing or installation.

The manufacturing benefit comes from repeating a coordinated configuration, not merely from repeating the same apartment label on a drawing.

What Must Be Coordinated Before Manufacturing Design Is Fixed?

Module Geometry, Structural Grids and Clear Height

The architectural grid and the module grid must be coordinated, although they do not need to be identical.

The design team should review module dimensions, structural depth, floor-to-floor height, achievable clear height and space for building services alongside the transport envelope. Local changes in structural grid or module position may be possible, but they can introduce additional connections and manufacturing complexity.

A workable architectural layout must also be checked against the actual transport and lifting constraints.

For French projects, achievable clear height may affect the applicable RE2020 calculations. The project team should assess this alongside structural and MEP requirements, rather than treating a regulatory calculation reference as a universal minimum dimension.

Façades, Shared Circulation and Structural Cores

A permanent volumetric apartment building may combine factory-built residential modules with conventionally built or otherwise prefabricated elements.

These can include stair and lift cores, shared corridors, basements, podiums and communal areas. The precise division depends on the structural system and project design.

The interfaces between these components deserve early attention.

Module-to-core connections, façade joints, weatherproofing, fire compartmentation, acoustic separation and service penetrations must all be coordinated at the whole-building level.

A varied façade is not inherently incompatible with volumetric construction. However, architectural variation may introduce additional interfaces or module configurations, affecting manufacturing repetition and installation.

Bathrooms, MEP Risers and Module Connections

Bathrooms and kitchens often concentrate plumbing, ventilation and electrical requirements within a relatively small area.

Drainage falls, supply routes, ventilation connections and vertical service risers must be compatible with the module layout and its structural boundaries.

Connections between modules, and between modules and shared building services, should be defined before manufacturing begins. Access for inspection, maintenance and final commissioning also needs to be considered.

A bathroom constructed as part of a complete volumetric building module should not automatically be described as a separate prefabricated bathroom pod. These represent different product scopes and may involve different technical evidence and contractual responsibilities.

Which French Housing Requirements Can Affect Project Suitability?

Planning Approval, Technical Evidence and Local Responsibilities

A permanent modular apartment development must be assessed under the applicable French planning and building requirements.

Local planning provisions, the permis de construire process and the work of the appointed architectural and engineering teams can influence the building layout, façade design and overall delivery strategy.

The contrôleur technique, where appointed or required, contributes to the prevention of technical risks. This role should not be confused with the authority responsible for planning permission.

Likewise, CE marking for an applicable construction product is not a building permit and does not establish compliance of the completed building.

MiC is not a separate French regulatory approval category. The technical evidence needed for a proposed building system depends on its actual configuration, intended use and the applicable project requirements. Technical assessment and insurance considerations may also influence its acceptance.

These matters should be established with the responsible French project professionals rather than inferred from the fact that the system is factory-manufactured.

Fire, Acoustic and Accessibility Performance

Structural stability, fire safety, acoustic separation and accessibility must be demonstrated for the actual building configuration.

For volumetric apartment developments, this includes the interfaces between stacked modules, shared circulation, structural cores, façades and service penetrations.

French residential fire requirements vary with building height and configuration. Certain tall buildings may fall within the immeuble de grande hauteur (IGH) framework, requiring additional project-specific assessment.

Accessibility also affects module planning.

French residential developments must address the applicable provisions for accessible and adaptable dwellings. Under Article L.111-1(13) of the Construction and Housing Code, a logement évolutif is a dwelling designed to permit specified future accessibility adaptations through simple works.

The technical meaning of those works is further defined in Article 16 of the 24 December 2015 accessibility order, as amended in 2019. In particular, qualifying adaptations must not affect structural elements or require certain interventions to shared technical shafts and associated building services.

For volumetric design, these requirements can influence bathroom positions, circulation, door openings, service routes and module boundaries. They should be considered during configuration planning, not left until after manufacturing design is fixed.

RE2020 and Whole-Building Environmental Performance

RE2020 evaluates the environmental and energy performance of the building under the applicable regulatory framework.

For apartment developments, relevant considerations include energy demand, lifecycle carbon and summer thermal comfort. Factory manufacturing does not, by itself, demonstrate RE2020 compliance.

Neither heavy-steel construction nor off-site manufacturing should automatically be described as a lower-carbon solution. The outcome depends on the actual materials, building systems, environmental data, transport arrangements and project design.

Decree No. 2026-200 of 18 March 2026 introduced calculation adjustments related to average ceiling height and qualifying outdoor amenity spaces in residential buildings. These provisions apply to relevant building permit applications and prior declarations submitted from 1 July 2026.

The adjustments can influence the assessment of ceiling-height choices and features such as balconies, loggias and certain stepped terraces. They are regulatory calculation mechanisms, not exemptions from RE2020 requirements. Not every type of terrace qualifies, as clarified in the French government’s RE2020 guidance.

The applicable calculations should be confirmed by the project’s energy and environmental design consultant using the regulations relevant to the submission date.

Does Volumetric Construction Improve the Whole-Project Case?

Compare Construction Methods on an Equivalent Basis

A technically feasible module configuration does not automatically make full-volumetric construction the best delivery strategy.

Developers should compare full-volumetric, hybrid and conventional approaches against consistent project assumptions. These should include the same dwelling mix, a comparable floor-area definition, equivalent building-performance requirements and the same target handover date.

For a French residential comparison, the area basis should be stated explicitly. For example, surface habitable and surface de plancher should not be treated as interchangeable measurements.

The comparison should then account for differences in structure, façade systems, shared cores, factory scope, transport, installation, inspections and site works.

This is particularly important where the apparent advantage of repeated factory modules may be offset by complex interfaces elsewhere in the development.

Define Factory and Site Responsibilities

Volumetric construction changes how work is distributed between the factory and the building site.

An agreed factory scope may include structural components, enclosure, interior finishes and MEP installations. Site activities may include foundations, cores, module installation, inter-module connections, final testing and external works.

The actual division must be established for the project.

More work completed in the factory is not automatically better. Transport protection, access to connections, inspection requirements and the risk of damage during lifting can influence the appropriate level of factory completion.

The project team should establish who is responsible for each interface, inspection, connection and commissioning activity before comparing proposals.

Include Transport, Installation and Whole-Project Cost

Transport dimensions and weight, permitted routes, lifting arrangements and delivery sequencing influence both the design and the overall project cost.

For modules manufactured outside France, international transport and onward delivery to the site must also be considered within the overall delivery strategy.

A module price alone cannot establish whether a volumetric project is commercially attractive.

A meaningful comparison should account for design, manufacturing, transport, installation, site works, testing, commissioning, exclusions and risk allocation.

It should also consider whether the procurement and payment arrangements can support the necessary design coordination and manufacturing programme.

Potential cost or schedule advantages should therefore be assessed at project level, not assumed from factory production or rapid module installation alone.

When Should a Developer Consider a Hybrid or Alternative Method?

Full-volumetric construction may become less attractive when building geometry is highly irregular, manufacturing repetition is limited, transport is impractical or the building’s required interfaces undermine the proposed factory scope.

A hybrid approach can sometimes retain volumetric construction for repetitive residential areas while using other construction methods for irregular ground floors, shared cores or communal spaces.

The appropriate choice depends on how the different systems work together, not simply on how many modules can be included.

The following examples illustrate possible decisions during early project assessment.

Project condition Approach worth comparing Main questions to resolve
Repetitive residential floors above an irregular ground floor Volumetric residential modules combined with a different ground-floor structure Structural transfers, fire strategy, core interfaces and overall cost
Repeated dwellings with complex shared circulation Volumetric dwelling modules with separately constructed circulation cores Connections, compartmentation, MEP and accessibility
Highly varied floor plates and façades 2D panelised, precast component, hybrid or site-built construction Whether sufficient module repetition remains
Module dimensions conflict with transport or lifting constraints Revised module configuration or another construction method Whether a compliant transport, structural and installation solution can be established
Five checks for assessing permanent volumetric apartment construction suitability in France

Illustrative framework for comparing full volumetric, hybrid and alternative construction approaches in French apartment projects.

These scenarios are possible design and delivery strategies, not confirmed capabilities of any particular manufacturer’s system.

For example, a development with repetitive upper-floor apartments but a highly irregular ground floor may be a stronger candidate for a hybrid approach than for an entirely volumetric structure.

Conversely, a development with limited repetition, many unique interfaces and unresolved site access may offer little practical advantage from volumetric manufacturing.

Where no feasible and compliant solution can be established for a critical constraint, full-volumetric construction should not proceed solely on the expectation of factory-related benefits.

What Information Is Needed for an Initial Feasibility Review?

An initial assessment does not require the developer to have completed a detailed module design.

Useful starting information includes:

  • Project location, planning context and current design stage.
  • Architectural floor plans and a dwelling schedule, including T1, T2, T3 and other relevant types.
  • Building height, structural concept and any proposed module division, if already available.
  • Site access, transport and lifting constraints.
  • Applicable performance requirements, including fire, acoustics, accessibility and RE2020.
  • Target construction schedule, procurement route and expected scope of supply.

With these inputs, the project team can begin to assess whether a workable module family can be developed, which interfaces require further engineering and whether full-volumetric or hybrid construction merits more detailed investigation.

FAQ

Does one apartment always consist of one volumetric module?

No. One dwelling may consist of several volumetric modules, while apartments with different layouts may share certain module configurations. The number of dwellings should not be treated as the number of modules or manufacturing variants.

When should a developer compare full-volumetric construction with a hybrid approach?

A hybrid comparison is useful when repetitive apartment areas suit volumetric manufacturing but irregular ground floors, circulation cores or other project-specific spaces require a different construction strategy. The alternatives should be assessed on an equivalent whole-project basis.

Does factory construction automatically make an apartment building compliant with RE2020?

No. Compliance depends on the actual building design, environmental and energy performance calculations, applicable regulatory requirements and the relevant submission date. Factory manufacturing alone does not establish compliance.

Is permanent volumetric housing the same as temporary modular accommodation or container housing?

No. Purpose-designed permanent volumetric building modules, temporary modular accommodation and converted shipping containers are different construction approaches. A converted container can be designed for permanent use in some circumstances, but its performance and approval requirements must be assessed independently.

Assessing Your Apartment Development in France

Permanent volumetric construction is most useful when the building design, module configuration, regulatory requirements and delivery strategy can be coordinated into a workable whole-project solution.

For some developments, that may support a substantial volumetric scope. For others, a hybrid or different construction approach will be more appropriate.

GSMOD works with permanent heavy-steel volumetric modular building systems. If you are considering this approach for an apartment development in France, you can contact our team with your project location, architectural plans, dwelling schedule, performance requirements and current design stage to discuss an initial technical feasibility assessment.

Any proposed solution would require project-specific engineering, regulatory assessment and agreement on the responsibilities of the parties involved.